Case study "West Oaks Primary School"
Time scale and specifications
- Having worked previously with Leeds City Council they were well aware of the versatility of the RENOLIT ALKORPLAN membranes on new build projects.
- This project was different in that it was a refurbishment of a very poor low level roof that as leaking badly.
- Original specification asked for another felt overlay which had been attempted previously but failed and brought ‘hot working’ problems with the material as well as fire loading issues.
- The school would be occupied by children, so noise and site maintenance were a major issue.
- The Head Teacher wanted a the job finished before exams started and we had a four week window in which to work in.